Nearing completion of mechanical, electrical, drywall rough-in. Drywall installation is ongoing.
hi there,
It's been another month of exciting progress at The Otto. Construction continues across all levels, with approximately 130 workers on site each day. This month, the General Contractor reached several key milestones, including drywall installation on the lower levels and continued roofing activities on the upper levels.
We remain on track for anticipated delivery in late summer to fall of next year. As construction progresses, we'll continue to narrow the delivery timeline and we will keep you informed every step of the way.
Nearing completion of mechanical, electrical, drywall rough-in. Drywall installation is ongoing.

Interior framing and window installation are underway.

Concrete deck pours continue, with exterior framing starting soon. Roof installation on the east side is ongoing.

Crews are prepping the level for steel installation.
